M7.18 - First integration phase complete

Notes

This milestone represents implementation of sustainable links between the bibliography service and mark-up services developed by this work package, and Scratchpads.

The bibliography service integrations is achieved through a Scratchpads-to-RefBank harvester program.

The mark-up modules integration is achieved through the standard OBOE interface.

See the milestone report for implementation details and sustainability after ViBRANT.


Rescheduling

The original DoW submitted in 2010 gave a target date of 31 March 2013 for this milestone. For various reasons the milestone reporting date was rescheduled on several occasions. These changes are fully documented in the milestone report.

The milestone was finally confirmed as achieved in full on Wednesday 27 November 2013, though some components of it has been in place for over six months by then.